
Signs of a Collapsed Drain: What Should You Look For?
1 August 2026How KD Restored an Asbestos-Contaminated Rising Main in Kent
A complex rising main repair in Kent required far more than a conventional drainage response when licensed asbestos-containing materials were discovered on a failed asset. KD Drainage and Asbestos Ltd coordinated asbestos remediation, CCTV investigation, tanker operations, excavation, civil engineering and structural pipe rehabilitation through one accountable team.

Project SummaryFollowing the collapse of a rising main in Kent, KD was appointed to manage a complex £120,000 repair project for Cappagh Browne. The works included licensed asbestos remediation, robotic CCTV investigation, temporary flow management, 175 metres of UV structural lining and the installation of 14 metres of new 300mm high-pressure pipework. The complete programme was delivered within three weeks.
Table of Contents
Project at a Glance
- Client: Cappagh Browne
- Sector: Civil engineering
- Location: Kent
- Project value: £120,000
- Programme: Three weeks
- UV lining installed: 175 metres
- Pipe diameters: 300mm–340mm
- New high-pressure pipework: 14 metres of 300mm pipework
Rising Main Repair Kent: The Challenge
The project began following the structural failure and collapse of a rising main.
Initial investigations identified asbestos-containing materials on the failed asset. This immediately increased the complexity of the project because conventional drainage repair work could not continue until the asbestos risk had been properly controlled and the affected materials safely removed.
Further investigation identified several significant problems across the drainage network.
Crown Collapse
Sections of the drainage system had suffered crown collapse and complete structural failure, requiring detailed investigation before the correct repair method could be selected.
Loss of Pipe Integrity
Parts of the existing pipework had deteriorated to the point where the structural integrity of the drainage asset had been compromised.
Ground Erosion and Voids
Failure within the system had contributed to ground erosion and void formation, increasing the need for controlled excavation and civil engineering works.
Pitted Cast-Iron Pipework
Significant lengths of existing cast-iron pipework were heavily pitted and required structural rehabilitation rather than simple cleaning or localised repair.
Temporary Flow Management
The wider drainage network still needed to remain controlled while the failed assets were investigated and repaired, requiring tanker support and temporary over-pumping.
Licensed Asbestos
The presence of licensed asbestos-containing materials meant specialist controls had to be established before the drainage engineering phase could proceed safely.
Cappagh Browne therefore needed more than a standard drainage contractor. The project required a team capable of managing asbestos risk, wastewater flows, investigation, structural rehabilitation, excavation and reinstatement as one coordinated programme.
One Contractor and One Coordinated Programme
KD combined its licensed asbestos capability with its drainage, tanker, CCTV, lining and civil engineering services.
This gave Cappagh Browne a single point of responsibility throughout the project, from initial investigation and asbestos controls through to structural rehabilitation, commissioning and reinstatement.
Using one integrated contractor reduced the need for repeated handovers between separate specialist companies. It also meant that the sequence of works could be planned around the needs of each discipline rather than treated as a series of disconnected jobs.
Integrated Project Delivery
One Contractor. One Programme. One Point of Responsibility.
Combining asbestos remediation, drainage investigation, tanker support, pipe rehabilitation and civil engineering within one coordinated delivery team allowed each phase to follow directly into the next while maintaining clear project accountability.
Licensed Asbestos Remediation
Before the rising main repair in Kent could continue, KD’s licensed asbestos team established a fully self-contained working environment around the affected area.
The controlled enclosure incorporated the measures required for the asbestos-remediation phase, including:
- Negative-pressure management.
- Controlled access arrangements.
- Independent electrical and water supplies.
- Dedicated welfare provisions.
- Decontamination facilities.
- Independent air monitoring and clearance testing.
The Health and Safety Executive provides further information on licensed asbestos work and contractor requirements.
Once the asbestos-remediation phase had been completed and the required clearances obtained, the drainage engineering works could proceed.
CCTV Drainage Investigation and Condition Assessment
Following asbestos clearance, KD deployed CityFlex Combination Tankers, FlexLine Tankers and robotic CCTV survey equipment to assess the true condition of the drainage network.
The investigation identified multiple areas of crown collapse, severe deterioration and complete structural failure.
Robotic crawler-camera technology enabled difficult sections of the system to be inspected in detail, allowing the team to determine which areas required excavation and which could be structurally rehabilitated without conventional replacement.
KD provides specialist CCTV drain surveys for investigating underground drainage condition and identifying defects before a repair strategy is selected.
Control the Asbestos Risk
Specialist asbestos controls and remediation were completed before conventional drainage works proceeded.
Maintain Wastewater Operations
Tanker support and temporary over-pumping helped maintain control of flows while the failed drainage infrastructure remained out of normal operation.
Investigate the Network
Robotic CCTV equipment was used to establish the extent and location of structural deterioration throughout the system.
Select the Correct Repair
Each section was assessed to determine whether excavation, structural lining or replacement represented the most appropriate engineering solution.
175 Metres of UV Bluelight Structural Lining
The CCTV investigation identified 175 metres of heavily pitted pipework that was suitable for structural rehabilitation using UV Bluelight lining technology.
KD’s specialist lining team installed UV-cured structural liners through drainage assets ranging from 300mm to 340mm in diameter.
The complete lining installation was delivered within two days.
Rather than excavating and replacing the full 175-metre length, structural lining enabled the existing drainage route to be rehabilitated internally. This reduced the amount of excavation required and helped accelerate the overall programme.
KD’s dedicated Bluelight lining service uses specialist light-cured lining technology to rehabilitate suitable damaged and deteriorated underground pipework with considerably less disruption than conventional excavation. :contentReference[oaicite:1]{index=1}
Following installation, CCTV surveys were completed to verify the condition of the liners and support final commissioning.
Why Was Structural Lining Used?
Structural lining was selected for sections where the existing pipe remained suitable for trenchless rehabilitation.
This evidence-led approach meant that excavation was reserved for areas where replacement was actually necessary, rather than excavating the entire drainage route.
Benefits of the Rehabilitation Approach
- 175 metres of existing drainage structurally rehabilitated.
- Reduced requirement for open excavation.
- Faster installation across suitable sections.
- Less disruption to the wider site.
- Existing drainage routes retained where practical.
- Post-installation CCTV verification completed.
New 300mm High-Pressure Pipework and Civil Engineering
Not every section of the failed drainage network was suitable for trenchless rehabilitation.
Where structural failure was too severe, KD’s civil engineering team carried out controlled excavation and installed 14 metres of new 300mm high-pressure pipework.
The installation included thrust blocks at bends and connection points, together with the associated excavation, pipe connections and civil engineering works.
Once the new pipework had been installed, the drainage network was commissioned and tested to confirm that it was operating as designed.
The project demonstrates why complex rising main repair in Kent cannot always rely on a single repair technique. Some sections were suitable for structural lining, while others required conventional excavation and replacement.
Tanker Support and Operational Control
CityFlex Combination Tankers and FlexLine Tankers remained operational throughout the works.
Their role was essential to wastewater management and site resilience while sections of the permanent drainage network were unavailable.
Temporary over-pumping arrangements helped maintain control of flows until the permanent infrastructure had been repaired and commissioned.
KD’s combination tanker fleet provides high-capacity jetting and vacuum capability for commercial, industrial and drainage infrastructure work. :contentReference[oaicite:2]{index=2}
Once the restored drainage network had been successfully commissioned, the temporary arrangements were safely removed.
Project Outcomes
The complete project was successfully delivered within the agreed three-week programme.
- Licensed asbestos remediation completed safely and compliantly.
- Regulatory and Environment Agency requirements satisfied.
- Multiple collapsed drainage sections identified and repaired.
- 175 metres of drainage infrastructure structurally rehabilitated.
- UV lining installation completed within two days.
- 14 metres of new 300mm high-pressure pipework installed.
- Full operational capability restored.
- Temporary over-pumping safely removed.
- Complete project delivered through one accountable contractor.
The Value of Integrated Drainage and Asbestos Capability
Infrastructure failures become significantly more complex when asbestos-containing materials are discovered.
Using separate asbestos, drainage, tanker, lining and civil engineering companies can introduce additional handovers and make sequencing the project more difficult.
On this project, KD’s combined capability allowed the entire programme to be managed through one delivery team.
This provided Cappagh Browne with a clear route from investigation and asbestos remediation through to structural rehabilitation, replacement pipework and final commissioning.
Project Result
From Failed Asset to Fully Restored Drainage Network in Three Weeks
Despite the combination of structural failure, asbestos-containing materials, temporary flow requirements and significant rehabilitation works, the entire £120,000 project was delivered within the agreed three-week programme.
Frequently Asked Questions
What made this rising main repair in Kent particularly complex?
The project involved both severe drainage infrastructure failure and licensed asbestos-containing materials. This meant asbestos controls and remediation had to be completed before the drainage repair programme could proceed.
How much pipework was structurally lined?
KD installed 175 metres of UV-cured structural lining through pipework ranging from 300mm to 340mm in diameter.
How long did the UV lining installation take?
The complete 175-metre structural lining installation was completed within two days.
Was excavation still required?
Yes. Sections that were unsuitable for structural rehabilitation required controlled excavation and replacement. KD installed 14 metres of new 300mm high-pressure pipework as part of the project.
How were wastewater flows managed during the works?
CityFlex Combination Tankers, FlexLine Tankers and temporary over-pumping arrangements were used to maintain control of wastewater flows while the damaged infrastructure was investigated and repaired.
How long did the full project take?
The complete project, including asbestos remediation, investigation, structural rehabilitation, excavation, new pipework, commissioning and removal of temporary flow arrangements, was delivered within three weeks.
Do You Have a Complex Drainage or Asbestos Project?
KD Drainage and Asbestos Ltd supports commercial, industrial, public-sector and civil engineering clients with complex infrastructure works. From drainage investigation and tanker support to structural pipe rehabilitation, excavation and licensed asbestos remediation, projects can be coordinated through one accountable contractor.




